What the City of Barrie Charges to Permit Weeping Tile Work

Barrie has no fee line called weeping tile. Here are the Schedule K items that build the number, and what starting the work without a permit adds.

Published
September 27, 2026
Coil of black weeping tile pipe on gravel in an excavated trench beside a concrete foundation wall, with a shovel in the soil

There is no permit for basement waterproofing in Barrie called a weeping tile permit, and no line on the City’s fee schedule with that name. The number is assembled. Every building permit application carries a $20.00 pre-screening fee, and a Part 9 residential permit cannot come in under $178.48. Above that floor the City adds whichever Schedule K items match the work, and which ones those are depends on whether the trench runs inside the basement, outside against the footing, or both.

The City’s own list answers yes twice

Homeowners are told that drainage is exempt, that it is a repair rather than a construction, that nobody permits a French drain. The City of Barrie settles the argument in public. Its residential permit page carries a table of common projects with a yes or no beside each one, and two rows land on this job.

Under plumbing work: “Installing, replacing or repairing water or sewer systems (e.g. plumbing, drains, backwater valve) inside or outside a building.” Yes.

Under basements: “Repair/replace waterproofing for basements.” Yes.

The same page states the general position in one sentence: “Obtaining a building permit is the law.” The second row is the awkward one for anybody arguing about definitions, because it does not care whether the work happens indoors or in a trench against the wall.

The fee is assembled, not looked up

Schedule K of the Fees By-law holds the amounts. These are the 2026 approved figures for the items that touch a footing drain job:

Schedule K item2026 fee
Pre-screening, non-refundable$20.00
Minimum permit fee, Part 9 residential building$178.48
Alterations and repairs to Part 9 residential, per square metre$8.19
Plumbing alterations, including backflow, per building$301.67
Manhole, catch basin, sump pump or pit, each$42.64
Underpinning$405.61
Grading review, projects not subject to site plan, condo or subdivision review$579.43

Read it as a menu rather than a bill. Schedule K tells staff to work out the occupancy and the scope, multiply the listed rate by the appropriate measure, add the additional rates where they apply, then check the total against the minimum. It closes with a line worth quoting to anybody who claims to know your fee in advance: the Chief Building Official “may determine appropriate fees where not listed in the schedule or where special circumstances warrant different fees.”

Which additional items apply is a question about your house, not about the trade. A new sump pit picks up the pit line. Underpinning is a separate item and only arrives if the footing itself is being underpinned, which an ordinary replacement does not involve. The grading review line is written for projects that are not already inside a site plan, condominium or subdivision review, so it becomes live on an exterior job that changes lot grading on an established street in Allandale or Letitia Heights.

Where the new system is allowed to discharge

The part that surprises people is in a different by-law, and it decides the design before it decides the price. Barrie’s Sewer Use By-law, section 3.3, reads: “No person shall discharge stormwater or uncontaminated water from drainage of roofs or building foundations, including sump pumps; or from land or watercourse or dewatering activity into the municipal sanitary sewer system unless authorized to do so by the City.”

Foundation drainage is named there in the by-law’s own words, and so are sump pumps. The definitions section reaches the pipe itself, describing a private sewer connection as any drain or system of drains “including drains or subsurface drainage pipe for surface or subsurface drainage of the land in or adjacent to a building”. Subsurface drainage pipe laid beside a footing is weeping tile written in a solicitor’s vocabulary.

So if the tile under your house currently runs to the sanitary sewer, replacing it is not a like for like reconnection. The water has to reach the storm sewer, or a pit and a pump discharging to grade, or the City has to authorise the sanitary connection in writing. Those are three different jobs at three different prices, and a quote that does not say which one it assumes is not a quote yet. The same logic is why a backwater valve in Barrie is a permitted installation here rather than a plumbing errand.

What starting early adds

Schedule K prices that outcome too, which tells you how often it happens.

  • Work begun before the permit was issued on a Part 9 residential building, where no Stop Work order was raised: a $178.48 surcharge on the application.
  • A Stop Work Order on a Part 9 residential building: 25% of the total permit fee, with $500.00 as the minimum.
  • An Order to Comply: $500.00.
  • Re-inspection of defective or incomplete work: $196.34 each time.

The cash is the smaller half. An interior system is buried under a re-poured slab and an exterior one under backfill, so the inspection has to happen while the trench is open. Miss that window and the choice is to open the floor again or to own a drainage system the City has no record of, which is the version that surfaces years later when somebody asks what was done to the basement and nothing on file answers.

Four questions before you sign

  1. Whose name goes on the permit application?
  2. Which Schedule K items does the quote assume, and is the municipal fee inside the price or passed through at cost?
  3. Where does the new system discharge, and does that route need the City’s authorisation?
  4. At what point does the inspector see the open trench, and does the schedule leave room for it?

None of that tells you whether the footing drain has actually failed, which is the decision worth getting right first, because a permitted replacement of a working system is still a wasted replacement. Our page on weeping tile replacement in Barrie sets out how we confirm it before anyone digs, and the cost of basement waterproofing in Barrie is set out separately. When you are ready, start your basement waterproofing Barrie quote and say what year the house was built and whether the basement has a pit.

FAQ

Related questions

Do I need a building permit to replace weeping tile in Barrie?

The City of Barrie publishes a yes or no table of common residential projects, and this job appears in it twice. Installing, replacing or repairing water or sewer systems, including drains, inside or outside a building is a yes. Repairing or replacing waterproofing for basements is a yes. Neither row makes an exception for drainage work.

How much is the permit fee?

There is no single number, because Schedule K of the Fees By-law has no weeping tile line. The floor is a $20.00 pre-screening fee plus a Part 9 residential minimum of $178.48, and the City adds whichever additional lines match the work. Schedule K also allows the Chief Building Official to set a fee where special circumstances warrant one.

Who applies for the permit, me or the contractor?

The application names an applicant, and that is a question to settle in writing before any deposit changes hands. Ask whose name goes on it, whether the municipal fee is inside the quoted price or passed through at cost, and who is responsible for booking the inspection.

What happens if the tile was already replaced without a permit?

Schedule K prices that outcome. A Part 9 residential application for work that started early, where no Stop Work order was issued, carries a $178.48 surcharge. A Stop Work Order costs 25% of the total permit fee with a $500.00 minimum, an Order to Comply is $500.00, and a re-inspection of defective or incomplete work is $196.34 each.

Talk to a Barrie waterproofing contractor

Barrie Basement Pros needs two things: where the water shows up, and when it started. That is usually enough to say whether you are looking at a downspout and some regrading or a drainage system — and we would rather tell you the cheap answer on the phone than sell you the expensive one at the door.